← All tools

Tools · Survey and earthwork

Earthwork cross-sections

Paste cross-section levels, set the formation level and template, and get every section drawn with cut and fill areas, volumes, a mass haul diagram and a DXF you can open in AutoCAD.

1. Levels data

11 cross-sections read, 99 level points.

2. Formation level

3. Section template

Presets are typical starting values. Check widths and slopes against the current RDSO formation guidelines or IRC:SP:73 / IRC:SP:84 for your project and soil.

Cross-section

CH 0/000
L20L15L10L50R5R10R15R2099.099.5100.0100.5101.0101.5CL · FL 99.600toe -5.50toe 6.25
GroundFormation and slopesFill (bank)Cut
Formation RL
99.600
Ground RL at CL
100.400
Cut depth 0.800 m
Fill area
0.00m²
Cut area
9.66m²
Toe to toe
11.75m
L 5.50 · R 6.25

Quantities (average end area)

Total fill
3,551.4m³
Prismoidal: 3,463.9 m³
Total cut
136.3m³
Prismoidal: 96.3 m³
Net
-3,415.1m³
Borrow needed
ChainageFLGLCut m²Fill m²Cut m³Fill m³Mass m³
0/00099.600100.4009.660.000.0
0/02099.64099.5820.410.20100.72.098.7
0/04099.68098.5790.0010.054.1102.50.3
0/06099.72097.9890.0018.540.0285.8-285.5
0/08099.76097.1680.0031.340.0498.7-784.3
0/10099.80097.1860.0033.110.0644.5-1,428.7
0/12099.84096.9810.0036.070.0691.7-2,120.5
0/14099.88097.7130.0025.410.0614.8-2,735.2
0/16099.92098.2060.0017.890.0433.0-3,168.3
0/18099.96099.3400.004.970.0228.6-3,396.9
0/200100.000100.2123.150.0031.549.7-3,415.1
Total136.33,551.4-3,415.1

Mass haul diagram

-3,41500/0000/200

The DXF has every section stacked one below the other, at the vertical scale chosen above, on layers GROUND, FORMATION, TEXT and DATUM.