Levelling: height of instrument vs rise and fall, with the checks

How to reduce a level book both ways, the arithmetic checks examiners love, and when each method is better.

A level gives a horizontal line of sight. Staff readings taken along it give the reduced level (RL) of each point relative to a benchmark.

Readings in a level book

  • Back sight (BS): first reading after setting up, usually on a point of known RL.
  • Fore sight (FS): last reading before moving the instrument.
  • Intermediate sight (IS): anything in between.
  • Change point (CP): a point with both an FS and the next BS.

Height of instrument (HI) method

HI = RL of point + BS RL = HI − (IS or FS)

Check: ΣBS − ΣFS = Last RL − First RL

Quick, good for many intermediate sights such as longitudinal sections and contouring. The check does not test the intermediate RLs.

Rise and fall method

Compare each reading with the one before: if the new reading is smaller, the ground has risen.

Rise = previous reading − current reading (if positive)

Checks: ΣBS − ΣFS = ΣRise − ΣFall = Last RL − First RL

Slower, but every RL is checked, so it suits precise work such as fixing benchmarks.

Worked example (HI method)

Point BS IS FS HI RL
BM 1.525 101.525 100.000
A 2.110 99.415
CP1 0.985 1.870 100.640 99.655
B 2.240 98.400

ΣBS − ΣFS = 2.510 − 4.110 = −1.600

Last RL − First RL = 98.400 − 100.000 = −1.600 ✓

Common errors

Staff not vertical, bubble not centred, parallax, and reading the staff upside down. Keeping back sight and fore sight distances equal cancels collimation error and most curvature and refraction.